  1. Site Layout: Prior to construction, we will layout the outline of the swimming pool that we have designed for your.  With your approval, we are ready to begin the dig process.
  2. Excavation: This will begin the construction process.  We will remove existing soil and shape the swimming pool to your design specifications.  Time to complete:  one day.
  3. Steel Installation: Rebar is installed forming the floor and walls of the swimming pool, giving shape to your pool design.  This will ensure strength and durability to your pool.  Time to complete: one day.
  4. Stub Out: Plumbers will install main drains and returns in the shell of the pool.  Time to complete: one day.
  5. Gunite: Gunite is pneumatically applied under high air pressure to guarantee the life and durability of your pool.  time to complete: one day.
  6. Plumbing: Plumbers will return to install the equipment and complete the plumbing process.  Time to complete:  one day.
  7. Electrical: Our licensed electrician will hook up your equipment which includes lights, filtration system, and any other items that may have been added.  Time to complete:  one day.
  8. Tile and Coping: We begin by installing the tile you have selected in the pool's interior, also known as the waterline.  Once the tile has been applied, we start installing the selected coping around the perimeter of the pool on the topside of the beam.  Time to complete:  three to four days.
  9. Decking: Your selected decking will be applied around the outside perimeter of the pool.  This is begun by setting forms, digging piers and beams, as well as installing deck drains.  Once completed, your deck is ready to be poured.  Time to complete:  three days.
  10. Plaster: Your pool is now nearly complete.  The final stage is to apply your selected plaster and begin to fill the pool with water.  Time to complete:  two days.

From Our Clients

Thanks for Your Support

sponsorshipDear Eddie,

first let me say, on behalf of The Woodlands Dynasty Girls Basketball program, thank you so very much for being a sponsor at the Inaugural Dynasty Golf Tournament, Sunday May 2nd, 2010.  As a reults of your sponsorship, we were able to raise $3,100 for our teams to go to the Tx STATE Tournament in San Antonio in July.

 

 

 

 

All Star Pools

21641 E Knox Rd, Suite A
Porter, Texas 77365

Phone: 281-354-3780
Fax: 281-354-5780

Kingwood: 281-354-3780
The Woodlands: 832-878-7041
College Station: 979-676-3780

Summer Spa Specials

kingwood spa special discount houston spa discount special bryan spa discount special the woodlands spa discount special

Memberships & Affiliations

Proud Sponsor Of: